Work is progressing on the UAB School of Nursing as concrete pours are underway for the new addition. With concrete work beginning two months ago, the pours for Levels 1 and 2 have been completed and Level 3 was poured just last week. As the new 5-story building inches upward, the pours will continue with the 2 remaining levels and the roof to finish it out.
The project team is working hard and continuing their efforts as construction moves forward. Keep up the great work!